Brice Engineering Shrinks Explosives Plume at Cornhusker Army Ammunition Plant

BRICE ENGINEERING

Subsidiary: Brice Engineering

Client: USACE Omaha District

Location: Grand Island, NE

Dates: 2018 – 2025

Since 2018, Brice Engineering (Brice) has been leading groundwater monitoring and remedial actions at Operable Unit (OU) 1 at Cornhusker Army Ammunition Plant (CHAAP) in Grand Island, Nebraska. Consisting of several OUs, each with unique contamination histories related to explosives manufacturing which began during the Second World War and continued through the Vietnam conflict, CHAAP has been listed on the National Priorities List since 1987.

The work Brice has performed over the past 8 years, working under four consecutive Task Orders with the USACE Omaha District (totaling over $10M), has achieved a significant reduction of explosives contamination in groundwater, credited to the effectiveness of Brice’s treatment strategies. The once 5-mile-long explosives plume is now less than 1 mile in length.

As part of the initial Task Order in 2018, Brice performed groundwater modeling that showed the explosives plume is stable and that subsurface injection for enhanced bioremediation will significantly expedite remediation of the explosives plume compared to the existing pump-and-treat system. Following a rigorous regulatory approval period, the Brice designed subsurface injection program was initiated in 2019 and included 2 years of injection, followed by 3 years of monitoring.

As a result of Brice’s successful subsurface injection program, the pump-and-treatment system was turned off and an additional 2 years of subsurface injections, followed by 3 years of monitoring was awarded by USACE Omaha in November 2024. In parallel with the subsurface injection program, Brice is completing a Proposed Plan and Record of Decision Amendment to officially change the OU1 remedy from pump-and-treatment to subsurface injection for enhanced bioremediation and monitored natural attenuation.

In June 2025, only six months following award of the additional subsurface injections, Brice began installing 600 injection wells throughout the OU1 explosive plume utilizing three direct push drill rigs. Over 325 tons of bioremediation amendment were delivered to the site in 20-ton tanker trucks and mixed with water. Two injection manifold systems, each with a high pressure pump and thousands of feet of injection hose, were used to inject the treatment solution at 12 injection wells simultaneously. Injection flow rates, pressures, and volumes were closely monitored by the Brice team to ensure the subsurface injections were executed in accordance with the design parameters. Each injection well received approximately 1,000 gallons of treatment solution (total of 600,000 gallons of treatment solution injected).

Our team completed the 2025 subsurface injection fieldwork on time, under budget, without incident, and with every member of the team providing strategic contributions. This achievement embodies the strength of our family-built culture. Our uniquely agile approach allowed us to go through planning, approval, preparation, and execution of the remedial action in half a year to keep the project on schedule. Despite this rapid pace, exemplary quality was achieved and the excellence delivered to our client reinforced our reputation as a trusted partner.

Follow on sampling is scheduled in 6 months to evaluate the performance of the subsurface injections. Preliminary groundwater modeling of the completed injections predicts that the site remediation timeframe will be reduced by 5 to 8 years.

We look forward to continued progress at CHAAP as we monitor treatment performance and move steadily toward site closure.