Brice Environmental Delivers Agile Solutions for Environmental Remediation at Tooele Army Depot

BRICE ENVIRONMENTAL

Subsidiary: Brice Environmental

Client: APTIM

Contract Value: $5M

Location: Tooele, UT

Date Completed: August 2025

Brice Environmental recently completed a challenging project at Tooele Army Depot South in Utah, serving as subcontractor to APTIM on a $5 million contract. While the work was primarily construction-focused, it contributed to environmental remediation by supporting the construction of protective soil covers over 100+ former munitions disposal sites.

The project addressed two Solid Waste Management Units (SWMU 1 and SWMU 25) where the Army had previously disposed of chemical and conventional munitions. A previously conducted Corrective Measures Study, selected construction of engineered soil covers as the site remedy to prevent exposure to uncharacterized waste and further degradation to groundwater.

Brice’s scope focused on mining, screening, and hauling approximately 250,000 cubic yards of soil from an on-site borrow area to support construction of the multi-layered soil cover systems. Our team worked for 100 days with a crew of about 10 people and a fleet of heavy equipment including four articulated haul trucks, a scraper, excavator, bulldozer, water truck, screen plant, loader, and motor grader. The goal was to haul about 3,000 cu yd per day to keep the project moving forward.

The soil covers required multiple layers each with precise soil specifications. The operations layer was installed first as a safety buffer, followed by a subgrade layer that required 2-inch minus soil. Next came a geosynthetic clay liner to prevent water infiltration, then a low plasticity protective soil layer, and finally a protective armor rock layer.

Finding Solutions on the Fly

What made this project stand out was Brice’s ability to adapt quickly to challenges as they emerged. Site Superintendent Brett Foster led the boots-on-the-ground effort, figuring out how to meet aggressive daily hauling targets while manufacturing soil that met varying specifications for different cover layers.

Since no intrusive work was allowed on site outside of the borrow area, Brice couldn’t cut the ground surface to build haul roads. Instead, Brice had to haul material in, dump it on the roads, and compact and grade it to create safe routes. The team also conducted soil testing on the fly to identify which materials from the borrow area would meet specs for each layer.

One of the biggest wins came when Brice identified an on-site source for armor rock that could replace the off-site material originally specified. Brice worked with the installation to get approval to use this material, then subcontracted about 15 on-road dump trucks to haul it from the on-site rock source. This saved significant costs and time compared to hauling material from 30 miles away.

Agility in Action

This project highlighted one of Brice’s core strengths: the ability to move quickly and adapt. When the team needed a screen plant or another haul truck, they made a phone call and got it on site fast. Brice’s streamlined decision-making process allowed the team to respond to challenges in real time without getting bogged down in lengthy approval processes.

Project Manager Andrew Castor noted that this agility was critical to success. “We were able to adapt to the environment out there and figure out what was needed. Our ability to quickly pivot and change, to work with the installation and use our relationships there—that’s what made the difference.”

The project wrapped up safely and on schedule in August 2025, delivering an optimal solution while protecting both human health and the environment at this former chemical weapons depot.