Tunista Construction Advances Civil Work for New Neah Bay K-12 School and Tsunami Shelter
TUNISTA CONSTRUCTION
Subsidiary: Tunista Construction
Project: CFSD Neah Bay School K-12
Client: Cape Flattery School District, Makah Tribe
Contract Value: $16.7M
Location: Neah Bay, Washington
Dates: June 2025 – September 2027
Tunista Construction is helping build a safer, stronger future for students and families in Neah Bay, Washington.
In June 2025, Tunista began civil construction work for the Cape Flattery School District’s new K-12 school. The $16.7 million design-build project will serve the district and the Makah Tribe, creating a new school facility that will also double as a tsunami shelter for the remote coastal community.
The project site began as about 16 acres of timberland on the Makah Indian Reservation in the far northwest corner of Washington state. The land includes a 13-acre main school site and a 3-acre laydown area planned for a potential future athletic field project.
Tunista was brought in early during design to help solve the site’s topographic and environmental challenges. The wooded hillside has more than 140 feet of elevation change, requiring major clearing, excavation, and grading to prepare a balanced site for construction.
Tunista is responsible for the full civil scope, including design consultation, clearing, earthwork, storm, water and sewer utilities, erosion control, concrete curb, sidewalks, asphalt paving, and landscape improvements. The team also completed important environmental work, including new wetland construction and improvements to a fish-bearing stream in May 2026.
Neah Bay’s remote location required careful planning for equipment, materials, food, and lodging. The project also required the team to build a local labor force to meet 50% TERO requirements.
Weather added another major challenge. Neah Bay receives about 105 inches of rain each year, and one inch of rain across the site can create about one million gallons of stormwater. To prepare for the rainy season, Tunista installed erosion controls and completed about 500 linear feet of 24-inch dispersion drain to help manage stormwater in compliance with Washington State Department of Ecology requirements.
The team also worked closely with geotechnical and civil engineers to balance the site without importing fill material, saving the project millions of dollars. When the native material compacted more efficiently than expected, Tunista helped develop an alternate excavation plan to source additional material from the hillside instead of importing costly borrow material.
Despite the remote location, steep terrain, heavy rainfall, and evolving design, Tunista prepared the site for winter weather, maintained strong stormwater controls, and completed all major earthwork milestones ahead of schedule. The project is scheduled for completion in September 2027.
When finished, the new Cape Flattery School District K-12 school will provide more than a modern learning space. It will also serve as critical community infrastructure for one of Washington’s most remote coastal communities.
For Tunista, the project reflects what our teams do best: solve complex challenges, protect the environment, and build infrastructure that serves communities for years to come.